Business case complete. Broad political support. Legislation needed.
As at 23 October 2026. Six years in the making. The scheme now waits on a Cabinet decision and enabling legislation, with every major party signed up to some version of it and a general election on 7 November 2026.
Funding councils
$2.5m round, 2025
Councils with in-principle support
RAS council engagement tracker, October 2026
Of 67 councils engaged so far
Funding, in-principle support or briefed
General election 2026
No Cabinet decision before then
Done
Milestones so far.
Business case delivered November 2025. Eight funding councils, 16 with in-principle support, positive indications from Government, LGFA board on board. No Cabinet decision or bill yet.


February 2026
Sector show-of-support round. Councils asked to pass in-principle resolutions before the Minister decides.

November 2025
Final business case and one-page overview delivered to Government, endorsed by an independent Strategic Advisory Group.

10 July 2025
$2.5 million funding round closes oversubscribed. Eight funding councils plus a $400,000 repayable grant from EECA.

21 March 2025
Minister of Local Government Simon Watts writes to LGNZ supporting the RAS and confirming DIA policy work from August 2025.


27 November 2023
Tauranga City Council approves up to $600,000 of development funding. Steering group: Auckland, Hamilton, Tauranga, Wellington, Christchurch, LGNZ and LGFA.


2019 to 2020
Development begins with LGNZ, LGFA and Cameron Partners, originally as the Ratepayer Financing Scheme.
Now
Political and institutional support.
Named councils, LGNZ's position and ministerial statements, each with its source.
Ministers have asked officials for advice on the business case. Cabinet has not yet considered it.
Minister Watts, March 2026: "I won't be commenting further at this time while it is being considered."
National, Labour and the Greens have each built election policy on the RAS. Election day is 7 November 2026.
National's Home Energy Fund (25 June 2026) and Labour's SolarSaver (8 July 2026) both include the $7 million Crown establishment stake. The Greens offered 15 votes to pass it before the election.
The Prime Minister, asked in the House whether the RAS would be implemented: "Absolutely."
21 July 2026 sitting. Quote taken from a Hansard digest search snippet and not yet verified against the full record.
LGFA's board has approved in principle up to 20% ownership, a debt facility, preference share investment and management of a RAS bond programme.
Subject to LGFA shareholder approval.
LGNZ aims to establish the RAS by the end of 2026 with first loans in 2027, subject to a Government decision.
Scott Necklen on RNZ Nine to Noon, 25 March 2026.
Next
What has to happen, and who has to do it.
The sequence as the scheme describes it: Cabinet, legislation, LGFA shareholder approval, councils join, establishment board, first loans.
Central government
- Cabinet decision on the business case and the Crown's role.One-off $7 million equity stake (19.9%), a standby liquidity facility and proximity to secure a very high credit rating.
- A standalone Ratepayer Assistance Scheme Act.Enables the RAS levy, defines how it operates, ensures transparency and coordination with council systems, and provides tax exemptions. Precedents: Local Government Borrowing Act 2011 and the Infrastructure Funding and Financing Act.
- Rewiring Aotearoa's open letter asks the next Government to prioritise RAS legislation in its first 100 days.
Local government
- More councils pass in-principle resolutions.Councils are asked to signal support before the Minister decides.
- Councils invited to join as members and subscribe equity.Members sign a limited joint and several guarantee proportionate to their ratepayers' use, provide website access and share data. Shareholders invest equity. Councils' at-risk development funding converts to equity, possibly on preferential terms.
- Councils adopt policies and pick products.Each council opts in product by product. Some will consult through their Long Term Plan or Annual Plan.
Others
- LGFA seeks shareholder approval for its stake and debt facility.
- EECA builds installer accreditation and the customer journey for Energy IMPACT loans.
- Banks engaged on the RAS levy ranking ahead of mortgages.Cameron Partners told Hutt City this had not yet been navigated with the banks.
- Establishment board appointed. First loans six to nine months after Cabinet approval (RAS overview) or 12 to 18 months after legislation (LGNZ).
RAS overview, November 2025; Whakatāne council deck, February 2026; LGNZ FAQ; Hutt City briefing, June 2025.
Business case done. Legislation next.
Council tally
28 of 67 councils engaged so far.
Statuses come from the RAS team's council engagement tracker and the public record.
Funding council
Support in principle
Briefed
Yet to be briefed
Key sources: RAS overview, November 2025; LGNZ RAS page and FAQ; Whakatāne council deck, February 2026.